Hi,
While transferring data from SAP PS to MS PRoject, the scheduled dates of activities are not being copied correctly.MS Project is showing the scheduled dates starting Project start date(Although the schedulded and basic dates of various WBS Elements are different).
My requirement is that the dates in MS Project should be exactly the same as dates in SAP PS
Regards,
B.P. Singh
I'm trying to guess here not sure if it will help.
Check below if you are using Open PS:
1. Ensure that 'Transfer Scheduling Information' is selected in OpenPS4MSP
Settings -> Object Types.
2. Indicator 'Schedule Automatically' is checked for networks in R/3
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sreenivas,
The checkboxes you have mentioned are already checked.
I think the reason is :
While transferring the project from SAP R/3 to MSP
You have to select one of the following two options:
Schedule from start or finish.
I think because of this only,the start date of all WBS Elements is the Project Start date.
Regards,
B P Singh