SCM-APO-PPDS

Former Member
0 Kudos

During the production planning run (/sapapo/cdpsb0) , when a simulation version is specified in the

along with the other selection screen data , no fixing intervals are transferred to the optimizer and

hence several activities are rescheduled. But if we do the same production planning run without the simulation version , the fixing intervals are transferred to the optimizer as expected.Kindly let me know why is t so ??

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

pl check if this has to do with the resources being version dependent...

did you copy over your 000 version resources to the 007 version or is it using resource parameters that is version independent

Former Member
0 Kudos

Hi Rekha,

My understanding was that the fixing intervals gets copied across to the simulation version in case you have an existing planning version by the same name (as the simulation version). e.g. if the simulation version is 007, you need to have copied across version 000 to 007.

regards

Vinod