on 03-24-2008 9:00 AM
at the time of confirmation of Production order by CO11n i get error : No Price could be determined for Object Activity Types 1000/1031101/43003, where 1000 is comtrolling area, 1031101 is Cost Centre and 43003 is activity. i have check all the possible best ways to solve.
please help its urgent.
Hi
IN KP26, Activity types to be planned for a particular cost center by giving the price of activity type for the period.
If you can not do it, pl. coordinate with your CO collegue & carry out this.
Regards
YMREDDY
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the solutions i checked the costings values per month through out the fiscal year i found for 10,11 & 12 month there was no values.
Thanks for youe reply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Yuvraj,
1.Check the validity Date of the Activity Type - in T code KL03.
2.Check the validity dates of the Cost center under Costing tab in Work Center in CR03.
3.For the common valid from date of this activity type,Cost center maintain the rates in T code KP26.
For Eg: If the activity Type is valid from 01.04.2007 to 31.12.9999 and the cost centre assigned in the work center is valid from
01.06.2007,then a rate can be maintained for the period say 03,2008 to 12,2008 in T code KP26.This is as per the Financial Year
Calculation.
I hope by the above checks you will be able to sort out the issue.
Regards
Mangalraj.S
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.