is there standard report to check actual (GR) based on project/ WBS

Former Member
0 Kudos

Hi All,

Is there any standard report to check actual based on project / wbs. At the moment i know the tcode CJ74.

Is there any other report ?

Thank you.

Best Regards,

Denis Evitanto

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please find the following actual reports of the project.

1. KSB5 - Actual Costs/Revenues

2. CJI3 - Actual Costs/Revenues

3. S_ALR_87013542 - Actual/Commitment/Total/Plan in CO Area Currency

Hope the above will help you.

Best Regards,

Rakesh Pradhan

Former Member
0 Kudos

Dear Rakesh,

It is really helpful, could you provide some detail for report S_ALR_87013542

What does it mean for Plan field?

Thank you

Nies

Former Member
0 Kudos

Hi,

Report (S_ALR_87013542) is most effective report for projects as planned cost / actual cost / Project profitability will be obtained from there.

Planed cost of the project will be obtained from the report. E.g. if you are doing project costing through Cost elements, in the mentioned report, all the cost planned through various Cost elements will be obtained. After posting actual cost to project, there can be comparison of planned cost Vs actual cost.

Hope this will help you.

Best Regards,

Rakesh Pradhan