Hi,

Can any one tell me that in a real time scenario can we execute both CTP as well as Multi Level ATP check at a same clients place (i.e in a same Project) ?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

First let me tell you this, I haven't worked on these in real time project(implementation).

Accroding to my understanding CTP is used when the production resource is critical and MATP is used when there is infinite capacity with availability of components is critical.

What do you mean by having these two at a same client place?

For the same product you can't have these two checks at the same time.Since the check mode decides which production type(CTP or MATP) you wanted to use and you can have only one check mode assigned to your product master(ATP tab).

If you are going to execute ATP check at different locations then you have a possibility of assigning another check mode & Business event combination thorugh location determination activity(/SAPAPO/RBA04).

For more information on this refer help.sap.com.

Regards,

Deepthi