on 03-21-2008 3:00 PM
We are installing EP 70 over Win2003 R2 64 bit
Enterprise Edition on a server with XEON CPU's.
THe server is a node on and MSCS cluster.
The installation of the latest Oracle patch 10.2.0.2 is hanging.
The Oracle Installation windows does not says 'Finished successfully', despite the log under the InstallAction log file there is as last item the row:
"......ended successfully"
Can we really consider the installation ended successfully and go ahead ?
regards
Hello Marco,
you can check the following things.
Run the "runInstaller" of the patchset again and click on "Installed products"... there you can check if all of your components are 10.2.0.2.
If there is all correct, you can execute the following statement:
> sqlplus "/ as sysdba"
> startup nomount;
> select * from v$version;
If all these components are showing 10.2.0.2, you can go ahead with the "Postinstallation Tasks". (startup upgrade, run catupgrd.sql, and so on...)
Regards
Stefan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.