Dear experts,
As per my business requires, we need to create inspection lot while transferring material to materil using 309 mvt type.
Is it possible? How to achieve this?
Regards,
Santosh
309 uses 08 inspection origin. Add the 08 inspection type (usually associated with 08 inspection origin) to the material, make sure you mark the activate checkbox in the material master. Make sure you have the appropriate plans set up for inspection.
Try it, it should work. if it doesn't, make sure someone hasn't deactivated QM for the 309 material movement in config.
Craig
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Santhosh
you can achieve by maintain unflag the 'No active' in the Inspection for goods movement and maintain the inspection type is 08
Regards
S.Anbu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Santosh,
Check in transaction OMJJ whether "Deactivate QM" for 309 movement is active, if so please deactivate.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.