Multiple project assignment to Appropriation Request

Former Member
0 Kudos

Hi

I have a situation where I need to attach multiple projects to a single appropriation request i.e. I would like to create a single appropriation request to plan and approve multiple projects. Can this be done in SAP? If so, how can this be done?

I would really appreciate quick response. Please treat this urgent.

Thanks,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Steve,

You can attach multiple projects to a single AR. In the measure/asset tab in AR (IMA11) you'll have to enter level 1 WBS of all the projects you want to attach to this AR.

while Using 'Transfer plan values to project function' you can tell the system the percentage of total AR plan value to be transferred to each project attached.

As for Approval, AR will be approved as a whole and for each project you will have to map their approval in PS itself.

While mapping user status for the AR you may tell the system that creation of project from AR or assignmemt of already created project to AR is forbidden until some particular status is activated (as usual)

with regards,

Ravi Shrivastav