PS Budget Report S_ALR_87013558 shows negative available amount

Former Member
0 Kudos

We activated Availability control in our Project System. We created a project, WBS elements, network activities. Then setup the budget (WBS level) then release the budget. Purchase requisitions were made to PO items, some were receipted and some are still in Commitment. We also added the cost for Travel and Accomodation but haven't posted any actual cost for these network activities. Then when I generated S_ALR_87013558 the budget available amount shows a negative balance.

I already run CJEN to reconstruct the table, CJBN to recontruct the availability control balance but it still generating the same negative available balance.

We setup our tolerance limit to raise an error once the budget reached 100% but in this case it should already been triggered before reaching zero but it didn't happen.

Any solution for the problem is greatly appreciated.

From this going forward any cost that need to be added to the project triggers the error message BUDGET EXCEEDED! it supposed to been triggered before the negative available amount on the report was reached.

The report show that I have an amount presented on the following columns:

ACTUAL

COMMITMENT

REMORDPLAN

ASSIGNED

I already checked the individual network activities to checked if the balance showed in the RemOrdPlan is correct using the formula REMORDPLN = MAX(0, PLAN - (Actual+Commitment)) and it is consistent with the amount presented in the report.

I will give points to anyone who'll shed light on this issue.

Kind regards,

Jo

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Jose,

I know this thread is very old. I am facing the exact same problem now. Can you please share with me how you solved it? It will be very helpful as I am facing exactly the same situation. Can you throw some more light on RemOrdPlan column?

Your reply will be extremely useful. Please help.

Regards,

Lakshmi

Former Member
0 Kudos

Hi

Thanks for excellent explanation. I feel, it is a std feature of SAP. unfortunately, i could not test now.

Kind sugestion is that, please post this question AGAIN in Project System group where many PS consultants can look through and help you..

Thanks