hi sap gurus,

i had done quotation to ps and attached bom created in cso1 to project in cn33.and went tp project and tried to calculated costs. it is showing error, in my network i have two activities where one is internal and external.for external it is calculting the costs but for internal it is showing errors.that the object could be calculated...

can any one suggest me the whole cycle linking with the sd and ps.

with regards

saju

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Actually account assigned sales orders r there in PS - SD so use WBS element to find G/L's

also costs to be brought to sales from PS via the DIP profile...

so that u can sue resource related billing and then from this resource related billing doc u create the SD billing doc.

U can find dip profile in Spro - Sd - sales - Sales doc - Cust service - -dip

so use dip and assign to item category and then when costs arise for this are transferred via this dip to resource related biling DP90 / 91 and then wwe can bill in SD via VF01 using this Billing reqyuest no. or resource related bill

Reward Points if concept clear for goinmg ahead further

regards

krishna

Former Member
0 Kudos

HI SAP GURS,

relevence of WBS element in SO with little further

how to chk with reference of SO No: or WBS to chk vice versa

where we r maintainng the DIP Profile

differnce and relevence of WBS and DIP profile

apart from DIP & WBS is there any link between SD with PS

any document related to above is required

thanks in advance

Former Member
0 Kudos

The main link between SD & PS is WBS element. WBS element is maintained at line item in Sales Order. Based on WBS the Cost & Price can be captured.