Dear Sir,

We have Make-to-Order scenario . We are using PS and PP both . Our problem is that we do not know about how to see the manufacturing completion progress in the PS . Without having any information related to Progress , the utility of PS becomes very small .

Kindly guide me on the issue .

With Thanks and Regards

B V Mittal

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

You can see the progress of the whole project and at each WBS level using (Percentage of completion).

Progress tab is available at WBS and activity levels.

Type of POC calculation method needs to be selected here-

-Cost proportional

-Revenue proportional etc.

CNe1, CNe5 transaction will help u assess the(Percentage of completion).

For this you need to "Maintain assignment of cost element group" under progress in spro.

Also default settings for Production order type for type of POC calculation method can be configured in 'Enter Measurement methods for Order type' under progress in spro.