on 03-19-2008 11:44 AM
HI All,
In my production order when during confirmation i have set when the qty is entered in the rework field during confirmation ., it will create a rework prodn order automatically by using trigger point.,
When it is created automatically the routing is copied and BOM is not copied
pls help me to solve this
Regards
Anand Srinivasan
Hi,
In rework order, there is no need to copy the BOM as in rework scenario, required components are not pre decided but you need to do GI for rework order.
So no predefined BOM needed but you need to issue components as and when need by your process.
revert back in case of any clarification.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pradeep,
I will reward the points,
for a rework order a ref opn set is assigned and also bom assigned to ref opn set ., when triggering the rework order is created and also the routing is copied
my doubt is why the BOM assigned to the ref opn set is not copied
Also i have tried a rework order (PP03) by creating manually here the BOM is copied how ?
Regards
Anand Srinivasan