Product Substitution ( Material Determination) in Project Systems

Former Member
0 Kudos

I have been using Product Substitution in Sales Orders. Can anyone inform me how to use them in Project Systems. Say, while adding material in CJ20N, I want the material to be automatically substituted by the substitute material.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Follow-up material gets automatically selected in networks if follow-up material is maintained in MRP4 view of material master. However, product substitution what you have mind could be something else ?

Muraleedharan.R

Former Member
0 Kudos

Hi Murali/Sid

I am also stuck with the same confusion if material Determination is applicable to PS.

I am getting the substitute material as a subitem with the same reservation number but the requirement is generated for the 1st item.

I want the requirement to be generated for the second item.

Pls guide if u have figured out something...

Regards

Praveen B.K