Cost element planing CJR2

Former Member
0 Kudos

hi,

how to plan the cost elements(CJR2) in INR while the controling area currency is EURO

regards

pavan kanchi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In the planning layout you use the key figure is usually set to 'Total Plan Costs in CO Area Currency'

In your case you may need to create a new planning layout/profile with 'Total Plan Costs in Transaction Currency'.

In the layout set the Characteristic Trans. Currency (INR) after moving the filed Trans. Currency from available to selected. There should be no errors in the layout.

Use this layout in planner profile and use this planner profile.

You also need to have exchange type/conversion thing sorted out.

Regards

Sreenivas

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Cost planning can happen in transaction currency if the transaction currency is activated in planning profile. Generally in cost planning profile, planning currency is in controlling area currency. Please check your planning profile in transaction OPSB, then change it to transaction currency which will allow for cost planning in transaction currency.

Hope this will help you.

Regards,