Dear All
I have one issue is,
our Factory calender is sun weekly off , for that when we create the notification and malfunction start date and end date is breakdown hrs. The Brd. Hours including the Weekly off, Is it possible to get Excluding the weekly off in Breakdown hrs?
Pls Reply
With Regards
Edwin
Hi Charles,
What you asking is not possible in standard SAP system. Because the code for calculation of breakdown duration is just the subraction of Malfunction End time and Malfunction Start time.
If you want the breakdonn duration excluding weekly offs you can go for Z-report where you can find work off days between Malfunction Start date and Malfunction End Date and subract it from actual downtime calculated by system.
Regards,
Narendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Experts
Pls give some valuble solutions for the above issue
Regards
SMC
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.