on 03-13-2008 7:39 AM
Dear all,
How can i change Horizon period from month to days,
where is the setting for this
thanks
Hi Vardarajan,
Its very simple, in OMO1 , double click on S066 - Open orders: credit mgmt, IN PERIOD SPLIT you will see the defaulted value as Month.
Go and change this to Day.
Also ensure that Updating is set to - Synchronous Updating (1)
Reward points for contribution if helpful
Regards
Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
It is in LIS .. Look at infostructure if iam not wrong it is S066 there u can change the update control from months to days...
Reward if useful
Krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Go to OMO1 transaction>>>select S066 infostructure>>double click on that>>>select radio button of Days option>>system will through u a information message stating>>> (Info structure contains data.If you change the period unit,this data will be lost.)
I think this would not be the right way of doing it...
Thanks & Regards,
Shaik Hussain.