on 03-12-2008 10:48 PM
Hi Expert,
It's possible to create a planned independent requirment of a product X for all the plants of the group.
Hi,
It is possible through SOP. Use level by level planning
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please refer this lnik:
http://help.sap.com/saphelp_47x200/helpdata/en/a5/631a8b43a211d189410000e829fbbd/content.htm