on 03-12-2008 3:09 PM
Hi PS experts,
My client has an issue pertaining to actual cost reports. The cost element report shows actual costs $42,000 for one WBS and when I double click to see details the value it shows is $2100. Even when I checked line item report for this WBS the value is $2100. What could be the reason for getting different values? If some one throw some light on this it would be great helpful to me
Regards,
Laxminarsimha
Possible reasons:
In cost Element report the selection parameters are in Fiscal periods and when you call the line item report by double clicking, the selection parameters (for line item) are not passed (some times) as the same,observe the posting dates/Cost Elements that appear in the line item report output.
There shouldn't be any difference as such, you can review the both the reports mentioning same parameters.
Better use CJEN and re-construct the Project Data Information data base and use value categories.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Laxminarsimha
The values in CJI3 should be correct and will include all postings (e.g. Settlement values) and possibly Actual Revenues unless a filter is in place - so take this as being your correct figure to start with.
Your drilldown will show the same value as CJI3 because it is CJI3
Any cost element report you are using is probably correct for what you are asking - is this a Standard Cost Element Report you are using or is it bespoke
One thing to be careful of when you drilldown on Cost Element Reports is that you do not always get the a make up of the value you have drilled down
e.g.
Cost Element Report was run for Period 1 to 6 2008 and shows £100.00
You drilldown and sometimes the drilldown automatically shows ALL line items e.g £500.00 (not just the values for periods 1 to 6 of 2008 which you may expect £100.00)
In the past I've removed the drilldown capability from bespoke cost element reports to prevent drilldown to the line item report (which is CJI3) because of this problem.
Usually where values for a a number of periods only (not total costs) was required
Other factors to consider
Revenues/Settlements may be excluded from Cost Element Report but will not be excluded from CJI3 unless you specifically restrict
You need to identify which types are postings are missing from the Cost Element Report (what is common...cost element, dr/cr indicator, business transaction)
I've also hit the mistake in the past where I've asked for periods 1 2007 to period 3 2008 and instead of giving me just over a years worth of actual it gave me actuals for periods 1 to 3 for 2007 and 1 to 3 for 2008.
Hope this helps
Steve
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Steve,
Thank you very much for detailed explanation.
We are using standard cost element report i.e S_ALR_87013543. I run the report for a project, for one of WBS the value is $42,000 for cost element 600001.
Then I run CJI3 for the same period, WBS and cost element 600001. The value is $2,000.
Why am I getting difference? If there is any filter, how do I check that?
Thanks in advance
Regards,
Laxminarsimha
Hi
By default there will not be a filter unless one has applied to the layout.
What I would suggest you do is the following
Run CJI3 for your cost element to get your value of 2,100 or whatever it was
Add the columns for Business Transaction and possibly Dr/Cr indicator to the report
Let me know what values are contained in the list (particularly interested in anything with KOAO)
I would then filter out anything with KOAO
Lets see if this gets your near the value of $42,000
Regards
Steve
Hi,
I did as per your reply, added Dr/Cr indicator column.
Under this column, some rows have value D- Debit posting or Receiver debit posting. The total value of these rows is $2500.
Remaining rows have value O - Special:Sender Credit from settlement. These value is $400.
So the net total is $2100
Regards,
Laxminarsimha
And you've already run CJEN? as per the earlier note...
Are you able to provide a dump (in Excel forma) of all records for the WBS from CJI3 including Dr/Cr Indicator/ Value Type and Business Transaction fields aswell as others you deem appropriate e.g Cost Element and Amount, Posting Date, Document Date etc
Steve
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.