Hi,
I want to upload Work break structures from SAP to a third party system,can anyone tell me what is the stardard IDOC for WBS elements.
Thanks
Hi,
Idoc type PROJECT01 can be used for WBS
Also refer
http://expertanswercenter.techtarget.com/eac/knowledgebaseAnswer/0,295199,sid63_gci983393,00.html
Thanks
swarup