Hi,
You need to have three system landscape in place to move request from development to quality and to production.
After creating the request you can use se01 or se09 or se10 to release the request.
First you have to release the attached tasks with the request by clicking on the task and then clicking on the icon (Van) made on it(release directly). after releasing all the tasks then you can release the main request in the same way.
once the Request has been released you can transport the request to Quality server by using TCODE stms in QA, client 000 with login DDIC.
Pls provide points if you feel it was helpful.
Rgds
Lalit RAna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.