Hi ,

i want to rerun RBA in BOP , but dont want to loose previous partial confirmation , is there any way to do ?

Ex

Mat1 quantity req = 100 confirmed 60

my SO appear as

10 100 main item requested quantity

11 60 sub-item confirmation

12 40 sub-item un confirm

I want to rerun rule in BOP only for sub-item 12 only .

I dont wana loose previous confirmation for 11 n nor i want any change in delivery date for 11 .

Is there any way to achieve this coz in re rule evaluation system consider main item .

Need urgent help .

Thanks n Regards