Hi ,
I am using Easy cost planning methodlogy for Cost planning.
I need some guidance on following points.
1. Can easy cost plan can be saved in versions ?
2. In CJ30 planned cost I can view in annual view but it doesn't get Summed up at Header level WBS ?
3.After releasing the WBS easy cost plan can be changed How to restrict that ?
Pl suggest.
Rgds
Hi,
1.0 You can use different costing variants to save your cost estimates. SAP recommends to assign a different valuation variant to every costing variant that you intend to use to save cost estimates.
2.0 To see the summed up cost plan in CJ30 , you have to first total up your planned cost in CJ40 thru' edit- total up.
3.0 SAP allows to change the cost planning even after the release. So I think this may be the case with Easy cost planning also.
Regards,
Amit More
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rasam,
Actaully the ECP itself does not have the verion function. There are two workaround.
1. The PS has the simulation functionality, using it, the ECP can be copied.
2. There are MECP (ECP with multiple versions), componenet EA_APPL, you can copy the ECP from one ( CO )version to another.
Kind regards,
Zhenbo
Hi Rasam,
You can see the ECP of simulation using CJ20N, or CJ9ECP.
The multiple ecp (MECP) is applied using SAP extenstion, after release 2.0. If you can check the system status of your system, you can find out, if the EA_APPL (at least 2.0 release) is applied your system or not. IF yes, you can find the corresponding customizing to active the MECP.
If MECP is active, you can then determine in which version should be ECP maintained. You get an additional POP UP screen to let you select the CO version, as you lauch to the ECP in CJ20N or CJ9ECP.
Kind regards,
Zhenbo
Hi Zhenbo,
I am generating purchase requisitions thru cj20n.( In easy cost planning )In requisition the account assigment appears for the WBS.
But while creating PO with reference of the requision system asks for the Account assignment where again I have to put the WBS element. I thnk this data shuld copied from requision.
Pl suggest.
Rgds
Hi Rasam,
for Point 3: You can have a user status for your WBS which will restrict the changes in the cost planning.
FATMAN
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.