on 03-08-2008 3:11 PM
Hi all,
I am able to get all the progress values in CNE5 for any project only if I explicitly mention a progress version in the progress tab of the WBS elements.
What may be the reason ? Do we have to assign the progress version anywhere in SPRO. We do not have this setting in Project profile.
Please Suggest.
Warm regards,
Srinivas Potluri
Hi,
In addtion to Venkats reply.. Progress version is controlling area specific and defines the control data for POC and earned values. It is mandatory to maintain progress version along with method of calculation. The system records progress analysis data in the progress version. That is why you can get the result only if you maintain it in the progress tab of WBS.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Well , in CNE1 while calculating the POC & EV, we specify the Progress version for which the values are required to be calculated.
I think there may be any other setting to default the progress version in WBS.
But anyway The progress values are getting calculated.
Thanks for your reply.
Warm regards,
Srinivas Potluri
SPRO->Project System->Progress->Progress Analysis-> Define Measurement Method as Default.
Here you define the Version, Object Type, Plan/Actual, Default Measurement Method.
After that Version would be defaulted for the object in the hierarchy.
Reward points if issue resolved.
Thanks,
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.