I am planning in APO PPDS for Finished Products which has more than one source of supply. I am running the infinite Planning for products, and after that all orders are scheduled on first PPM infintely.
and this is causing only a single resource overload, and even while finit scheduling system schedules orders only that perticular source of supply ( Resource). In case planned has to manually schedule the orders in DS planning board on other source of supply.
is there a way by which while planning all the source of supply will be considered so as to have most of resource utilized after planning run.
Hi
Can I ask why you are running the Infinite Heuristic for planning when you want the resources balanced, that seems like a conflicting requirement?
Regards
Ian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.