on 03-04-2008 10:12 AM
Hi All ,
Can anybody tell me how to make plant a required entry while creating a QN ? We have tried making it in screen template settings by selecting plant as required entry, But when creating a QN and though we input plant in plant for material field system is issuing a message to enter a plant and we could not able to find the same in QN other than plant for material field.Kindly give me a solution for this.
Thanks
Benny
Hi,
In SPRO settings , "plant for material" comes under reference objects screen & "Plant" / "Plant for work centre" under general screen.
Chech whether you have set the indicator for the required one.
Regards
K.M.Arun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In SPRO , under -reference objects settings, "Plant for material " field MAWERK listed twice , one with table VIQMEL & other with Table RQM00. I am not sure about this.
But when i refer in Notification for Plant for Notification field , it refers to RQM00 table. So you may try marking this (RQM00-MAWERK) field alone as required field & see how it works.
Regards
K.M.Arun