Hi All,
Can you please explain the complete life cycle of a project and the various integrations with FI,CO,MM,PP,SD,IM,PM.
This question is very important for any PS Consultant.
If you have any documents for this pls do farward me on muzamil.firdosi@gmail.com.
Appreciate for your quick answar.
Regards
Muzamil
muzamil.firdosi@gmail.com
Hello,
A project lifecycle can be described broadly as:
Project Initiation> Project Planning(includes structure, cost, staff planning)> Project Execution--> Closure
Throughout the life, project monitoring and control is required.
Mapping in SAP:
Creation of Project for quotation purpose>Preliminary planning> Quotation and pricing> Sales Order- order received>Detailed planning> Accruing of cost through material and time hours> Period End closing for control and reporting> Delivery from project> Billing--> Closure
Integration with FICO-- Cost planning/ budgeting/period end closing- RA, settlement, cost postings, billing
Intergation with MM-- PR, PO, Good issue, Project stock, Service procurement
Integration with PP-- Production order for network, BOM transfer, assembly processing
Integration with IM-- Investment projects for AuC creation, WBS as investment measure
Integration with SD-- Revenue planning, assembly processing, billing, delivery
Integration with PM-- Maintenance order with WBS assignment
I have tried to describe the vast and complex area of PS integration in a nutshell. It is very interesting and challenging at the same time.
Thanks,
Sourabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.