on 03-03-2008 4:45 PM
Hi,
I have kept in Latest start tab, Refer data/time as workitem creation and ten days as time period
so if the agent does not process the workitem in ten days the deadline notification will be generated
but what if the workitem is not completed even after ten more days ?
will there be no deadline notification?
so is there only ONE deadline notification created for the workitem ?
any help is appreciated......
thanks
R
Rita-
The short answer to your question is yes the deadline only occurs once. Once the deadline event is reached you can model follow-up escalations, etc. in the WF. These follow-on action can have its own deadline setting.
But to be clear that an agent won't continue to receive notifications for an item where the deadline is reached. It is a one time event which you build upon for the next required system action.
Regards-
b
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
There are 4 points to trigger deadline.
+ Requested Start
+ Latest Start
+ Requested End
+ Latest End
You can also model a process after deadline by changing workflow template.
Regards,
Masa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.