Hello All,
We are finding problems wherein CTM stops planning when there is a recursive BOm involved?
Please help.
Thanks,
can you expand on what you mean by recursive relationship ?
Based on my understanding planning engines do not take any cyclical relationships gracefully. Example an input of a Bill of Material or Bill of Distribution again becomes output in the relationship chain. One may have to do setup some dummy components to overcome this shortcoming.
Did the master data consistency check give any error at all ? Can you try to run piece-wise CTM (with different scope) and see if it works.?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.