Hi
Is there any way we can control the delivery of components from projects CNS0 using User statuses.
The components in project stock should not be delivered until the User status permits it.
Kindly advise.
closed the thread
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I do not know what exactly is your requirement. If you forbid "Goods Issue Delivery", it will prevent PGI (Post Goods Issue) of material, though it may permit creation of a delivery document. In normal business situations PGI is a more significant factor. You can review your scenario and requirement.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please create a user status with business transaction "Goods Issue Delivery" as forbidden , and assign the status to the WBS element.
It should work. I have not tried it out though.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.