Hi

Is there any way we can control the delivery of components from projects CNS0 using User statuses.

The components in project stock should not be delivered until the User status permits it.

Kindly advise.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

closed the thread

Former Member
0 Kudos

Hi,

I do not know what exactly is your requirement. If you forbid "Goods Issue Delivery", it will prevent PGI (Post Goods Issue) of material, though it may permit creation of a delivery document. In normal business situations PGI is a more significant factor. You can review your scenario and requirement.

Muraleedharan.R

Former Member
0 Kudos

Hi,

Please create a user status with business transaction "Goods Issue Delivery" as forbidden , and assign the status to the WBS element.

It should work. I have not tried it out though.

Muraleedharan.R

Former Member
0 Kudos

Hi

No, it dosen't stop the delivery. I had already tried it.

Regards

Former Member
0 Kudos

Try setting forbidden for Business Transaction SDDN-Create delivery

Regards