DSEX status for Network Activity

Former Member
0 Kudos

Hi,

1. How do I set DSEX status for Network Activity using BAPI?

2. How do I update scheduled dates for an activity once DSEX status is set, through BAPI?

Regards

Shrikant

Accepted Solutions (1)

Accepted Solutions (1)

abhishek_singh1
Explorer
0 Kudos

Dear Shrikat,

You may use the BAPI BAPI_BUS2002_SET_STATUS to set the status DSEX on an activity.

I think that once DSEX is set on an activity, it will not be considered during scheduling till you revoke the status.

You may use BAPI_BUS2002_SET_STATUS to revoke the status again.

Regards,

Abhishek

Former Member
0 Kudos

Hi Abhishek,

Thanx for ur reply. I am already aware about that BAPI but looking for functionality which PM order maintain BAPI provides. In that BAPI, if you pass X in constraints DSEX flag gets set. Later if you pass dates in constraint dates field, the scheduled dates get updated. So I am interested to find out how one can update the scheduled dates, once DSEX is set.

Regards

Shrikant

Answers (0)