Hi,
1. How do I set DSEX status for Network Activity using BAPI?
2. How do I update scheduled dates for an activity once DSEX status is set, through BAPI?
Regards
Shrikant
Dear Shrikat,
You may use the BAPI BAPI_BUS2002_SET_STATUS to set the status DSEX on an activity.
I think that once DSEX is set on an activity, it will not be considered during scheduling till you revoke the status.
You may use BAPI_BUS2002_SET_STATUS to revoke the status again.
Regards,
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Abhishek,
Thanx for ur reply. I am already aware about that BAPI but looking for functionality which PM order maintain BAPI provides. In that BAPI, if you pass X in constraints DSEX flag gets set. Later if you pass dates in constraint dates field, the scheduled dates get updated. So I am interested to find out how one can update the scheduled dates, once DSEX is set.
Regards
Shrikant