I encountered that the schedule line item has no confirmed quantity. What are the possible reasons these happened?
Thanks.
Hi,
Please check your MRP settings in the Material Master Record.
U need to give the Av check and TOR Configuration done in SPRO
Then it will give u material for future date even if it is not there in plant right now.
Reward if it helps
krishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Are you using product allocation. If so, if there is no allocation to that Sold party in MC94, then we will not get confirmed schedule line.
Kind Regards
Sandeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The 1st reason could be no stock ( can check using T.code .MMBE).
2nd reason could be not relavent for avaliability check ( check in VOV6 select the relavent scheduline category and check in transaction flow tab field availability if checked)
3rd reason could be either the customer is blocked for his credit.
Kindly Reward points if useful.
Regards
vK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.