What is Commitment date and Confirm date and what are the differences between both .
Thanks in advance
Regards
SK
Commitment date is the date on which the goods or materials have been promised/committed to deliver.
Confirmed date is the date on which the goods/materails was delivered or received.
Hope this helps.
Reward points for all helpful answers.
Thanks,
Balaji