Hello experts.

Created a lot of inspection for a material which had not assigned an inspection plan. The status of the lot is CRTD-CHCR-SPRQ. For the material was created an inspection plan, but efforts to change the lot does not determine that the inspection plan, delivering the message "No inspection plan could be found." What can be done? Delete the lot and create again?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

former_member42744
Active Contributor
0 Kudos

Check the key date on the inspection lot. (QA02). Make sure it is the current date. It must be later then the date you created the plan on.

Other things to check if that doesn't work:

- On the spec page of the lot look at what type of usage the lot is asking for. Make sure the plan you created has the same usage.

- Make sure the plan is released annd double check that the material is assigned to the plan.

- Make sure the UOM in the plan is the same UOM as the material in the lot.

- Make sure there are not any quantity limitations in the plan. (rare, not a lot of places change inspection plans based on inspection lot sizes)

There should be no need to cancel the lot. You just have to get the various parameters to match up to the plan.

Craig

Answers (1)

Answers (1)

Former Member
0 Kudos

Thanks Craig, i change the key date and works.