Table name for getting LEVEL 1 WBS element budget

manoj_goyal2
Participant
0 Kudos

Hi Guys,

Can anybody tell me the table name to get the LEVEL 1 WBS element YEARLY budget and OVERALL budget. Or is there any FM which can return the LEVEL 1 WBS element yearly budget and overall budget.

Thanks,

minisap

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Check the tables (below) against the OBJNR (of your 1st level WBS element)

BPGE Budget, overall cost

BPJA Budget, annual values

Regards

Sreenivas