on 02-28-2008 2:25 PM
Hi,
There is difference between In transaction CJ30 AND CJ74
In cj 30
Budget 23000
Assigned value 23015
But In TC cj74
Actual : 18000.
But it should be same. Why is difference ?
With regards,
v.k
Assigned values constitute of many things as below and not just actuals:
Actual costs of WBS element carrying budget
Statistical actual costs of WBS element carrying budget
Actual costs of subordinate WBS elements if these do not carry budget
Statistical actual costs of subordinate WBS elements if these do not carry budget
Commitments of WBS element carrying budget
Commitments of subordinate WBS elements if these do not carry budget
Maximum of plan and actual costs + commitments from assigned networks or orders
Debit from settlement to WBS element
Credit from settlement to budget-controlled WBS
You difference could be any of them.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't think you've got a column Assigned Values in Standard report S_ALR_87013560.
S_ALR_87013560- Is an Budget Update report (Which includes Original Budget,Supplement,Return etc.,)
If you have any doubt that assigned values are improper, better execute CJBN so that assigned values are recalculated and get reflected in reports properly.
Regards
Sreenivas
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.