I have a project whose budget and availibility control has been changed. Is there a way I can see what changes have been made to the budget and availibility control as well as the user id?
Regards
Hello,
You can check CJI8 for the budget line items. This will provide an overview on the different releases, returns, suppelements etc, performed over the original budget.
If status change documents are active, you can check change documents for status AVAC, ISBD, etc. This will provide an overview on the availability control changes.
Hope this helps
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Juliet,
You can get the document number in CJI8.However, if you select the correct layout in CJI8, you will obtain all the necessary information without the need of calling CJ3B.
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Changes in the budget or allocation of original budget values always generate a document and you can see then using T Code CJ3B.You can also see who has created the document.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.