Hello,

in your Network you can add 4 types of activities:

Internal processing

External processing

Costs

Services

What do they mean? and what can they be used for?

Thanks,

Renaat

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

SAP Project System supports the following activity categories.

• Internal Processing: for capacities to be staged in your own

company

• External Processing: for tasks to be assigned externally

• Service Activities: for procuring external services

• Costs: for planning additional primary costs.

You use the activities in the network to plan the labor, capacities, materials,tools, and services you require to carry out various tasks in your project. By assigning milestones to activities, you can document events that are particularly important for the progress of the project and reference their respective dates in billing or invoicing plans, for example. During the project execution phase, commitment and actual costs are updated automatically to the network activities as a result of various business transactions (for example, confirmations, ordering processes, goods issues, incoming invoices).

Hope this helps.

Regards

Tushar

P.S.Reward points for useful answer.

Edited by: Tushar Vhora on Feb 28, 2008 1:32 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

Internal activities are used to detail the work to be performed

External activities are used to purchase resources

Service activities are used to purchase services

General Costs activities are used to plan additional primary costs.

Hope this helps.