on 02-28-2008 11:28 AM
Hello,
in your Network you can add 4 types of activities:
Internal processing
External processing
Costs
Services
What do they mean? and what can they be used for?
Thanks,
Renaat
Hi,
SAP Project System supports the following activity categories.
Internal Processing: for capacities to be staged in your own
company
External Processing: for tasks to be assigned externally
Service Activities: for procuring external services
Costs: for planning additional primary costs.
You use the activities in the network to plan the labor, capacities, materials,tools, and services you require to carry out various tasks in your project. By assigning milestones to activities, you can document events that are particularly important for the progress of the project and reference their respective dates in billing or invoicing plans, for example. During the project execution phase, commitment and actual costs are updated automatically to the network activities as a result of various business transactions (for example, confirmations, ordering processes, goods issues, incoming invoices).
Hope this helps.
Regards
Tushar
P.S.Reward points for useful answer.
Edited by: Tushar Vhora on Feb 28, 2008 1:32 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Internal activities are used to detail the work to be performed
External activities are used to purchase resources
Service activities are used to purchase services
General Costs activities are used to plan additional primary costs.
Hope this helps.
Regards
Martina
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.