Hi all,
I have a question about resource planning in cProjects with RPA+WFD.
1. cProjects 4.0 run on CRM 5.0. We use SAP HR and transfer master data from there.
2. I have a Project with a Role (staffed by "Resource Manager via Authorization")
3. In IMG "Specify Demand types for Resource Planning" = Project Role Demand.
Also, I maintained "Project Profile for Scheduling" (Use Cost Rate, Use Qualification and Resource type = Internal/External Resources)
4. Run RPA:
- in "Resource Overview" I choose suitable resource (it has in cell assigned/available 0:00/8:00)
- in "Demand Overview" I choose suitable project (required capacity = 5,00)
- in "Assignments" I create assignment, in field "Duration" I set "5" and choose "Apply". After that system show 1 error and 2 warnings:
- Error in cProjects; Maximum allowed required capacity was exceeded
- cProject warning; Time was converted from 5,00 HR to 5,00 H - rounding errors are possible
- Required/Planned capacity of Demand does not match
Is anyone can help or may be you have a configuration doc?
Please, help!
Useful answers will be rewarded
PS. Time Unit in IMG "Basic settings" = "H". I change the value to HR, save, again look in this setting there is "H" again!
Thanks and Regards,
Konstantin Melnik
Partly solved.
Main problem I think in time unit.... <h6>But I'm not sure. Now I'm working in another client and there time unit is correct ("HR" instead of "H").</h6>
-
Another question.
When I make assignment the system says "Assignment generated with warnings":
"Assignment outside demand window for <such resource>".
Where I missed something?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
7 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.