We are having following scenario in our business process Dairy Industry:

- We are having 2 m/c on one proccessing line say Mixing and Packing

- Mixing happening in KG

- Packing happening in PC

- Planned order for finished good is genarated in PC and fed as input to PPDS run

- PPDS - PPM is having 2 operations for Mixing and Packing

Now my Query is

- How planned order in PC can be fed as a input to first operation Mixing as Mixing happening in KG's?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Are your code for output poducts in both the activity i.e. Mixing and Packing different?

In this case while defining the components for the activity you can give different UOM for Input and output as per you requirement.

After this define the activity relationship, I think this setting is enough to solve your problem.

Thanks,

Sanjog