cProjects to CATS integration

nirajsikligar
Active Contributor
0 Kudos

Hi

This is Niraj Sikligar.

Presently I am working on cProjects to CATS integration, but I am not been able to get work list for the resource being utilised in cProjects.

Does any one have the config doc / Implemantation guide for cProjects to CATS integration ????

Please send me the same on niraj.sikligar@lntinfotech.com

It will be of great help.

Thanks and Regards,

Niraj Sikligar

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Refer to

https://wiki.sdn.sap.com/wiki/display/PLM/HR_CATS_Cproject+Scenario

Niranjan

Award if Useful

let me knwo if it helps...

nirajsikligar
Active Contributor
0 Kudos

Niranjan,

In CAT2 I am not getting task in work list.

Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi,

You have to check following,

1. Project in cProject is assigned to organization.

2. in project type choose time recording via CATS

3. Business partner is created using Hr sync person so that there is a link.

Niranjan

Award points if useful

nirajsikligar
Active Contributor
0 Kudos

Hi Niranjan,

Whatever you have mentioned is already done, but I think the problem is with Data entry profile settings.

Regards,

Niraj Sikligar

Konstantin
Participant
0 Kudos

Don't you forget to release both projects: in cPro and PS?

If not try to describe your steps on configuring.

nirajsikligar
Active Contributor
0 Kudos

Hi Konstantin,

I have gone through settings for CATS, there it is mentioned that Data entry profiles to be created for "Specific settings for CATS for service Providers", but there I am not finding Time settings, Person selection, etc. Instead it is available in "Specific settings for CATS classic" .

How Can I find all the setting you have mentioned for Service provider in Specific settings for CATS for Service provider ??

Thanks and Regards,

Niraj Sikligar

Konstantin
Participant
0 Kudos

Oh! There is an error in the settings, excuse me please, quite forgot about it.

All settings do in "Specific settings for CATS classic".

nirajsikligar
Active Contributor
0 Kudos

Hi

I have created new Data entry profile in CATS classic as per your document.

But still I am not able to get the cprojects task in work list of timesheet.

Is any other settings am I missing ????

Thanks and Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi Niraj,

Did you:

1. Assign the role to the task in cProjects?

2. Release the task?

3. Maintained 105 infotype (User Name) correctly?

Are you using cProjects and CATS in the same server?

Konstantin
Participant
0 Kudos

Tell which of the controlling methods you use:

● Task-based or Role-based

● Account assignment object: Internal order or WBS element

● Manual or automatic

nirajsikligar
Active Contributor
0 Kudos

Hi Remya,

I have assigned Role to Task in cProjects, Released the task and I am working woth developer ID for the person so, I suppose I do not need to maintain infotype 105 for the person.

Is there anything to do with Data entry profile ?? I have created new Data Entry profile in CATS classic, Do we actually need to maintain the same in CATS service provider??? But in Service provider I am not getting certain field like Time units and From Project assignments.

And cProjects and CATS are on the same server.

Please help.

Thanks and Regards,

Niraj Sikligar

nirajsikligar
Active Contributor
0 Kudos

Hi

I am using following controlling method:

● Task-based

● Account assignment object: Internal order

● automatic

Please help.

Thanks and Regards,

Niraj Sikligar

Konstantin
Participant
0 Kudos

OK, let's repeat.

<h5>Settings</h5>

1. Project Type in cProjects (Collaboration Projects --> Structure --> Define Project Types), fields:

<h6>Scenario. = A Accounting Integration in mySAP ERP

Type of Transfer = 1 As of “Flagged for Transfer / To Assign’Automatic

Time Recording for = Tasks

Time/Travel Expenses Rec. CATS/SRM/FIN = X</h6>

2. In the accounting system you made general settings:

Transaction Code: SPRO

IMG Menu: Collaboration Projects --> Connection to External Systems --> Accounting Integration --> Make General Settings

in "Accounting Integration using Cost Collector in mySAP ERP" field

<h6>Object Type = Single-Obj. Controlling on InternalOrders.</h6>

3. In the accounting system you defined controlling scenario, field:

<h6>Controlling Method = Internal Order (Structure Element, Manual)</h6>

4. Replicate Accounting-Relevant Characteristics?

transaction code DPR_FIN_GECCO_R3_REP.

We are using scenario Single-Obj. Controlling on WBS Elements & Multilevel Controlling (Structure Element, Automatic).

We created new Data Entry profile in CATS classic, not in CATS service provider. In the latter we didn't do anything.

<h5>Process</h5>

1. You create the project, define and schedule it, define resource needs, assign resources.

2. Did you create a quotation and how did you do this if yes?

3. You should change the status of the project to "Set to assign" and save project. As far as i can see after that the internal order should to be created?

As any the project and the internal order number should be connected.

4. You should create sales order and assign internal order. (It is necessary for resource related billing).

5. And now in the worklist confirmation-relevant objects should be displayed.

Is all correct?

Konstantin
Participant
0 Kudos

Ouch! In Process i missed an important step!

Between step 3 and 4 must be another one: you should release the project!

The project, the first phase and the assigned tasks must be released. This is a prerequisite for time recording with CATS on cProject tasks!

nirajsikligar
Active Contributor
0 Kudos

Hi

Settings are as follws :

1. Project Type in cProjects (Collaboration Projects --> Structure --> Define Project Types),

Type of Transfer : Always Automatic when Saving.

Rest all the things in this field is as mentioned by you.

2. In the accounting system you made general settings:

Transaction Code: SPRO

IMG Menu: Collaboration Projects --> Connection to External Systems --> Accounting Integration --> Make General

Settings

All the settings same as mentioned by you.

3. In the accounting system defined controlling scenario, field:

My settings : Controlling Method = Internal Order (Project definition, Automatic)

4. Replicate Accounting-Relevant Characteristics?

transaction code DPR_FIN_GECCO_R3_REP.

Accounting-Relevant Characteristics replicated.

I am using scenario

Single-Obj. Controlling on WBS Elements & Single Object Controlling on Internal Orders

I have created new Data Entry profile in CATS classic.

1. You create the project, define and schedule it, define resource needs, assign resources.

2. Did you create a quotation and how did you do this if yes?

No Quotataion created

3. You should change the status of the project to "Set to assign" and save project. As far as i can see after that the internal order should to be created?

As any the project and the internal order number should be connected.

Internal Order is created but the costing data in not getting displayed.

Role assigned to task and released

4. You should create sales order and assign internal order. (It is necessary for resource related billing).

I am not using this functionality

5. And now in the worklist confirmation-relevant objects should be displayed.

Still the task related to cProjects not populated in work list of CATS.

Do I need to make all the settings same as you ????

Thanks and Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi Niraj,

Let me know if you are simulating this on IDES, and which version? IDES ECC6 has slighly different settings in Data Entry Profiles.

Regards,

Vivek Pandey

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

No I am simulating it on Client ECC6 server.

Simultaneously simulating it on IDEC server also, but theere also same problem...

If you can share any document please send it on niraj.sikligar@lntinfotech.com

Thanks and Regards,

Niraj Sikligar

Konstantin
Participant
0 Kudos

May be give a glance to suitable Best Practies?

In Best Practices for Project Service Delivery & Engagement Management w/ Multi Level Controlling (CO) (D82) i found:

<h6>"The Customer Sales Order has been created and the Internal Order has been assigned as the account assignment object. This means that all costs/revenues on the Internal Order is used for Resource Related Billing of the Customer for the services performed by the service provider."</h6>

Unfortunately our CO and HR consultants are inaccessible at now so i can't ask them if the Sales Order is is necessary for resource related billing.

Konstantin
Participant
0 Kudos
nirajsikligar
Active Contributor
0 Kudos

I have run the report with new CATS profile, with person no, and today's date and following is the output:

NO RFC FOR ALE Found, only O.K, if the cProject is installed in the same system

5 items selected in worklist

1 items removed from worklist because of no accouting object found

What does it indicate ??? And how to solve it ????

Thanks and Regards,

Niraj Sikligar

nirajsikligar
Active Contributor
0 Kudos

Hi Konstantin,

Any feed back on my reply ???

I am still not been able to see cProjects task in CAT@ work list.

Is there any problem with Data entry profile ????

Thanks and Regards,

Niraj Sikligar

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

I have run the report as suggested in the link which Konstantine has suggested.

Feedback of the report is as follows:

5 items included in work list.

But I am still not able to see those items in work list.

I think you also have run that report.

Is there any different settings for Data Entry profile as suggesteed by you earlier???

If it is so can you please send me those settings ????

Thanks and Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi Niraj,

Please send me a screenshot of your data entry profile settings to mailviveck@gmail.com.

I'll try finding out what needs to be done.

Regards,

Vivek Pandey

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

Sent you the screen shots.

Thanks for your help.

Regards,

Niraj

nirajsikligar
Active Contributor
0 Kudos

Hi

I have checked SAP # Note 1129336 - CATS integration: Worklist.

I have run the report and following is the output :

NO RFC FOR ALE Found, only O.K, if the cProject is installed in the same system

5 items selected in worklist

1 items removed from worklist because of no accouting object found

If items are selected in worklist, why it is not being seen in Work list ?

Can anyone suggest ????

Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi,

I had also similar problem for cProjects & CATS integration.

Please check your data entry profile properly. While making time entry in CAT2, you need to select the task / project assigned to employee. Then only actual time will get posted into cProjects. Please let me know if you are getting the project details while making time entry. After time entry check the CATSDB table for time entry details.

Hope this will help you.

Regards,

Rakesh Pradhan

nirajsikligar
Active Contributor
0 Kudos

Hi Rakesh,

For making time entries in CAT2 transaction I am not getting the project task in work list.

If you have solved this problem do let me know.

Thanks and Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi Niraj,

Please check your configuration in data entry profile for getting project details while making time entry.

In data entry profile of work list area select from project assignment. This will list project assigned to respective employee during time entry.

Hope this will solve yoour issue.

Regards,

Rakesh Pradhan

nirajsikligar
Active Contributor
0 Kudos

Hi Rakesh,

It is already done as mentioned by you.

Any other setting am I missing ???

Regards,

Niraj

Former Member
0 Kudos

Hi Neeraj,

One check:

Please ensure following fields are visible in yr worklist area ( Influenced by the data entry profile)

Project : CATSD-CPR_EXTID

Project Description: CATSFIELDS-CPR_TEXT

Project Subobject: CATSFIELDS-CPR_OBJTEXT

Do let me know.

Regards,

Vivek Pandey

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

All these fields are visible in CAT2 transaction.

Field selection : Influencing Field, for the the Worklist and Data entry section for data entry profile, fields you have mentioned are selected as "Display" mode in customizing. Other fields are in either "Input" or " Hide" mode.

Is that correct ???

Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi Niraj,

If you have maintained all the configuration properly, then actual time should transfered to cProjects after running report in SE38.

I will suggest debug the report in SE38 with your ABAPer so that actual issue can be identfied.

Regards,

Rakesh Pradhan

nirajsikligar
Active Contributor
0 Kudos

Hi Rakesh,

But first it should reflect in work list and then only I can transfer it to cProjects. isn't it ???

Any other suggestion ????

Regards,

Niraj Sikligar

Konstantin
Participant
0 Kudos

Hi Rakeh,

Before sending actual time items must be shown in Work List.

But Niraj don't see them. So Niraj can't record any time!

Or I've missed something?

Regards,

Konstantin

Konstantin
Participant
0 Kudos

Hi Niraj,

I send you my settings. May be this can help you.

nirajsikligar
Active Contributor
0 Kudos

Hi Konstantin,

Yes, I have received the same. I will do the same setings to my system and check if it work.

Thanks very much for the same.

Regards,

Niraj

nirajsikligar
Active Contributor
0 Kudos

Hi

I have tried with the settings you have sent. But still not able to see items in work list.

Is it required to create new project after I ahve done all the setings ???? and then see ??

Regards,

Niraj Sikligar

Former Member
0 Kudos

Hi,

You can make time entry against internal order created from cProjects. Afterwards you need to run the report in se38 DPR_CATS_CPR_TRANSF to post time from CATS into cProjects.

In se38, you can debug the programe.

Regards,

Rakesh Pradhan

Former Member
0 Kudos

Hi Niraj,

Did u make the relevant settings in Project Type config w.r.t Confirmation??

Please check and let me know.

Regards,

Vivek Pandey

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

Following are the settings :

Time recording for : Tasks

Time recording for project definition Ticked

Time /Travel expenses Rec.CATS/SRM/FIN Ticked

I tried to book the time against Internal order manually in CAT2 transaction but the data transfer to CO in CAT7 transaction is also not happening.

I think there is some issue with accounting integration.

If it is so, will this lead to work list not getting populated with task in CAT2 ??

What are the settings for activity type and cost element /cost element category in Cost and Activity type assignment ???

Please suggest.

Regards,

Niraj

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

I have come to one SAP Note # 913347 - CATS integration with cPro without ALE scenario

It says that :

Symptom

CATS cannot be integrated with cProjects in non-distributed scenarios.

Reason and Prerequisites

You are using the integration of CATS with cProjects. cProjects and CATS are not distributed, but run on the same instance. You can therefore not set up the ALE scenario.

Is there anything to do with my problem ???

Can you please tell me what is distributed scenario and Non-distributed Scenario ???

Regards,

Niraj

Former Member
0 Kudos

Hi Niraj,

When CATS and cProjects are lie in different systems, then you consider it as a distributed scenario.

For e.g you are using cProjects 4.0 and your base components are in 4.6C. In this case, both components will be on separate servers.

In case of non-distributed scenario, cProjects as well as base coomponents are on the same system. For e.g ECC6.

I guess the note will help you.

Regards,

Vivek Pandey

nirajsikligar
Active Contributor
0 Kudos

Hi Vivek,

I have cProjects and ECC 6.0 on the same server, so mine is non-distributed system

In that case this note should help me.

Can you please explain me about ALE scenario ?? How it can help me ???

Thanks and Regards,

Niraj

Answers (1)

Answers (1)

Konstantin
Participant
0 Kudos

Hi!

1. [help for cProjects ver.4.0|http://help.sap.com/saphelp_ppm400/helpdata/en/e5/d29f06b91b4b20a00102d924db9fda/frameset.htm]

2. [Setting up ALE to integrate cProjects with CATS|http://service.sap.com/sap/support/notes/954860]

3. And [settings for CATS|http://www.filefactory.com/file/167872/]

Regards, Konstantin.

nirajsikligar
Active Contributor
0 Kudos

Hi Konstantin

I think Settings for CATS file will solve my problem. I was not able to get project ID for the person in work list through Data entry profile which I think I would be able to do after maintaining settings mentioned in the document.....

Thanks very much.

Regards,

Niraj Sikligar

Former Member
0 Kudos

Dear Friend

i am looking for necessary setting required in CATS for integration of Cproject with CATS.

Regards

Sam

Konstantin
Participant
0 Kudos

Hi, Sam!

[954860 - Setting up ALE to integrate cProjects with CATS|https://service.sap.com/sap/support/notes/954860]

Regards, Konstantin