Hi,
I am adding WBS Number at account assignment field of Sales header, but the same is not transferred to item level.
I want to know, what setting is required for the same?
Regards
Suman
you have to do that on item level
you can assign sales order items or customer quotation items to a WBS element (billing element)
if you do, revenue and cost controlling takes place wholly within the project
the quotation/order does not bear either costs or revenues
the billing element referenced in the sales order item is the highest element in a billing hierarchy
the billing hierarchy includes all objects (WBS elements, orders networks, network activities) hierarchically subordinate to the billing element
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.