Dear All,

I need to add and additional operation in the inspection lot. Just as we can attach unplanned MIC to the inspection plan, here my requirement is to attach unplanned MIC in separate and new operation.

This is asked by a user to separate the Unplanned MICs in the insepction lot form the regular ones.

Pls help me out. How can I do such so?????

With Best Regards,

Shyamal Joshi.

Accepted Solutions (1)

Accepted Solutions (1)

former_member42744
Active Contributor
0 Kudos

So.. can't do. Not that I'm aware of. You'd have to customize the system for that.

Craig

Answers (1)

Answers (1)

Former Member
0 Kudos

hi joshi,

First u conform the inspection lot is realeased or not. If it is realeased do the following steps.

01) Go to inspection plan change mode and change what ever

u want.

02) Go to qa02 inspection lot change mode and select inspection lot in menu bar then select special changes and then select the reset sample . System resets the sample.

03) then reassaign task list and caliculate sample .go to result recording and record the results of the mics.

if it is useful dont forgot reward points.

regards

sankar

kaushik_choudhury2
Active Contributor
0 Kudos

Hi there ,

As per my understanding this is not as per the best practice......... please post the scenerio in which the following requirement as arisen.....

Thanks & Regards

Kaushik