on 02-23-2008 4:48 AM
Hello all,
I need one help regarding the Purchase requisition generation for HAWA materials from Projects.
I have attached one HAWA material to the activity with stock type as Non stock material. I have got the Purchase Requisition for that material as soon as i saved the project.
However When the same Purchase Requisition i want see in ME52n then it has given me the massage "Address doesn't exist %00000001 1000000568 00010" and it comes out of the transaction.
regards,
Sudhir
Thanks for the answer Mr.Murli,
Actually i have selected option 3 rd party order. Also i have entered customer no. and then saved the project. It generated the PR but when i am accessing the same PR with ME52n. It is giving me the error Address doesn't exist %00000001 1000000568 00010".
Regards,
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
When you attach a non-stock material ('N') to a network activity, two options come up:
1)PR for network
2)Third part order
If you opt for 3 rd party order (materials to be delivered to final customer, not to your stock), system asks for delivery address/ customer number while attaching the materials which should be keyed in . Pl check whether this has been done.
In any case, you can maually add the delivery address in PR (ME52N) by clicking the tab "Delivery Address" located at item level.
Muraleedharan.R
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.