Hello,
Is it possible to do workforce planning and timesheet booking for contractual labors?
Thanks
Hai Anjali
Yes its possible to do the workforce planning(CMP2/CMP9) and booking of timesheet(CAT2) for the contract labours provided the Contract Labours is mapped in ur HR module(PA40,PA30).
If not mapped u can plan just numbers while assigning the manpower in the internal activity.
Based on ur scenario could able to explain further
ENJOY SAP PS
Regards
PP