on 02-21-2008 4:13 AM
An item has zero quantity as checked in MMBE. Client is expecting that it will go to backorder processing. But upon , performing the availability check all of the quantity for the item in SO was confirmed on a certain date.
how does this situation happen? kindly advise.
Thanks,
Help please...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
this will happen as per the Availability check and TOR configuration.. even after activation of availability check if we activate the check with replenishment lead time (RLT) field in OVZ9.. the system will give confirmation on the end of RLT.
Hope you understand.. if you still have problem.. let me know..
reward points if useful
Muthupandiyan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
jisley,
as you told since the item has zero quantity upon doing availability check, the system depending on backward /forward scheduling would have calculated that the requested qty can be available only on a certain date and thus confirmed that date.
regards
sadhu kishore
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.