Inprocess inspection

Former Member
0 Kudos

Hi friends

Can u explain me how to carry out inprocess inspection?

How i can show rejection on a particular operation and that component i want to sent to rework ?

please help me in mapping this scenario

Regards

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi patil

In process inspection is possible in SAP but little difficult.

One suggestion.

Instead you split the halb material up to in-process stage as Halb1 and after in-process inspection stage as Halb2. Create seperate Material master, change BOM and Routing accordingly.

You can do QM lot procedure after GR production for Halb1 material. And with Result recorsing QE 50 with UD you manage Rework and Scrap by posting it to seperate storage location.

From that storage location you can handle Scrap and Rework.

Rework by Production order without material with order reference T code Co 07.

Regards

J .Saravan