From where i can get the cost center of the respective plant ??

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Parmar

A cost center can be assigned to only one company code. If you define a one-to-one assignment between controlling area and company code, you cannot enter the company code in the cost center master data. The company code is set by the SAP System. If the assignment is not one-to-one (cross-company-code cost accounting), you can enter the company code when you edit the master data.

Business area

When defining a company code, you can specify whether the SAP System should create a balance sheet or a profit and loss (P/L) statement for each business area. If you assign a cost center to this company code, you must also specify the assignment to a business area in the cost center master data

Also please note that:-

=> Several cost centers can be assigned to a company code.

A cost center is assigned to exactly one company code.

=> A cost center can be assigned to exactly one business area to which all costs of the cost center can be attributed.

=> One or several company codes can be assigned to a controlling area. A cost center is assigned to exactly one controlling area.

=> A cost center can be assigned to exactly one profit center to which all costs of the cost center can be attributed.

If you want to see the cost center details, run KS03

thanks

G. Lakshmipathi