Hi,
I am facing a scenario that the confirm date in my SO should be the date of the confirmation type LA (inbound delivery) in the corresponding PO. Now I have set up the schedule line cat with account assignment cat M and item cat 0. The PO can be created fine, so what should I do next so that when the LA exists in PO, SO confirmation date will get update? Thank you!
Regards,
Ming
Edited by: Lun Sheung Ming on Feb 20, 2008 9:16 AM
Hi
In the transaction OVZ9 , based on your checking rule ,you select the Tick mark ( Include Shipping Notification).
This will include all the Inbound deliveries in case for your PO.
Hope its useful for you.
regards
KRSNA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello all,
I'm facing the same problem where the material availability date in the sales order will not get updated by the LA confirmation date in the PO. It only get updated by AB confirmation. My ATP check does include shipping notification and I'm running on version ECC6.0. Any idea?
Also, is there somewhere in IMG that specifies which confirmation category (e.g. LA, AB) to be included in the shipping notification of an ATP check?
Appreciate for any input.
Thank you.
Lim