Purchase Requisition in Plan Driven Procurement

Former Member
0 Kudos

Hi experts

i'd like to know what is the procedure in Customizing in order to send the PR from ECC 6.0 to SRM 5.0 in Plan Driven Procurement.

Points for u

Thanks

Andrea

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Andrea,

For Plan Driven Procurement, on ECC, you need to maintain table entries V_T160EX and V_T160PR and schedule report BBP_EXTREQ_TRANSFER on ECC. V_T160EX determines which material groups are grouped into profile and V_T160PR determines which profiles target which RFC.

Check this too

http://help.sap.com/saphelp_srm50/helpdata/en/18/db183d30805c59e10000000a114084/frameset.htm

Regards,

Suren

Edited by: Suren on Feb 19, 2008 5:17 PM

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

These are Plan Driven Procurement - Prerequisites

SRM system settings

-


-> perform all steps for direct material

-> set up entry channel for external requirements

-> assing an RFC user for this entry channel

-> assign your local purchasing group as responsible for this channel

-> set up sourcing configuration

R/3 Backend settings

-


-> maintain tables V_T160EX and V_T160PR

-> make sure to have a RFC connection to the EBP system, with the same RFC user as in the entry channel (with SAP_ALL and SAP_NEW Profiles)

-> schedule report BBP_EXTREQ_TRANSFER to transfer the requisitions to EBP

After customizing the direct material, there are additional steps necessary:

-> Using an entry channel, the requisitions are transferred into EBP. This channel must have at least one

entry user.

-> Corresponding to this entry user, you have to set up a RFC connection from back end to EBP by using

this special RFC user.

-> To get the requisitions in the work list for purchase orders, or in sourcing, there is a local purchasing

group required with the responsibility for the entry channel and the product category of the back-end

requisitions.

-> Customizing of sourcing or a BADI decides if the sourcing transaction or the work list for purchase

orders will be used

-> View V_T160EX in the R/3 back end determines which material groups and purchasing groups are

grouped into a profile. View V_T160PR determines which profile targets to which RFC connection.

-> The transfer itself is carried out by the report BBP_EXTREQ_TRANSFER. These can be scheduled (for example, once a day.)

See these related threads/notes:

Note 656597 - External requirements not transferred to SRM

BR,

Disha.