on 02-19-2008 11:06 AM
Hi,
We have introduced pre-production environment.Now we need to configure 4 system transports.
How to configure 4 system transport landscape.
- Kristene
Hello,
You need two do 2 things:
1. Include the system into your existing transport domain.
2. Re-configure the transport routes
To include the system into your existing transport domain check the following link:
http://help.sap.com/saphelp_47x200/helpdata/en/44/b4a0c17acc11d1899e0000e829fbbd/frameset.htm
To re-configure the transport routes:
You simply need to login into the 000 client of your domain controller and re-configure your transport routes.
as described in the link given below:
http://help.sap.com/saphelp_47x200/helpdata/en/44/b4a1df7acc11d1899e0000e829fbbd/frameset.htm
Once you have re-configured the transport routes, do not forget to distribute the configuration.
Regards,
Siddhesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.